The Financial Times reports Oracle has promised investors it will continue
payments even if a large New Mexico data center fails to secure power before
going live. Insiders say Oracle has issued a force majeure notice to the
project's developer, a unit of Blue Owl Capital, over power-supply issues. The
project has faced permitting delays amid local opposition. Under contract terms,
if the first phase is not ready by a 1H 2027 deadline Oracle must cover a
holding-cost payment in lieu of rent for up to three years; one insider said
power-delivery risk is borne by Oracle, not investors.