The expansion of data centers in the United States continues to accelerate, with year-on-year growth in data center capacity reaching 4.4GW, 2.4GW, and 2.1GW in the PJM, ERCOT, and MISO power markets, respectively. Based on Aterio's latest project schedule, Goldman Sachs has revised its forecast for US data center power capacity by the end of 2027 from 90GW to 92GW, an increase of 28GW compared to the end of 2026, representing a year-on-year growth of 44%. The forecast has also been extended to 2028, with an expected additional 52GW of capacity coming online that year. Goldman Sachs also points out that since 2026, US data center capacity and power demand have grown by nearly 30%, contributing more than one-third of the increase in total US power demand. Continued expansion will further drive up US power demand, tighten regional power markets, and increase natural gas demand.