Goldman Sachs, using Aterio project scheduling data, estimates that U.S. data center capacity expansion will continue until 2028, but there is a significant gap between actual project implementation and planned capacity. According to the original project schedule, the cumulative capacity by the end of 2028 was approximately 225GW; after adjusting for project delays and cancellations, Goldman Sachs estimates it at approximately 145GW, a reduction of about 80GW from the original schedule; currently, approximately 115GW is operational or under construction. Another approximately 30GW of Goldman Sachs' projected capacity is not yet reflected in operational or under-construction projects, facing significant uncertainty regarding commencement and delivery. Goldman Sachs' latest forecast on November 24th also shows that new power supply capacity for U.S. data centers is expected to reach 18GW, 28GW, and 52GW in 2026, 2027, and 2028 respectively, with the 2028 increase nearly three times that of 2026. Goldman Sachs believes that data center expansion will further drive up U.S. electricity demand and increase natural gas demand.